The planned IP network comprising CCTV, passenger information system, passenger counting system, etc., with which the entire vehicle fleet is to be equipped, is working. At least in the laboratory. Now the task is to test it in practice under real conditions. This is being tested in a pilot project.

Content
From Proof of Concept to Pilot Setup
The pilot phase is a practical test under real operating conditions and, after the proof of concept (which we have already written about here), the next step in setting up the network infrastructure. The purpose of the pilot phase is to test the finished network concept, in which all devices have been defined, correctly set and successfully connected, in regular operation on several vehicles. The network created under laboratory conditions is now to prove itself in real operation on the bus or train.
A Practical Test Provides Important Findings
The new pilot network will be set up in a few vehicles as defined in the network concept and tested in productive operation for a certain period of time. The aim is to find out to what extent there is a need to adapt the systems.
In the practical test, the following questions, among others, can be answered:
- Can the vehicle equipment be fitted out as planned?
- Do the devices deliver all data as expected?
- Do terminal devices (e.g., cameras, passenger counting systems) need to be readjusted?
- Is there access to the network across the entire route or only at specific locations?
- When and where is diagnostic data needed?
- Does the operation meet the requirements?
- Does the application function as expected?
In general, it is important to scrutinize the pilot network as closely as possible in order to gain a lot of knowledge and experience as well as to uncover any problems. This will determine the success of the pilot phase. No open questions or unresolved conditions should remain after the test run, and the data obtained should be valid and meaningful.
Preparation for Roll-out
After the pilot network has been extensively tested and, if necessary, adapted, all configurations should be finalized, saved and made available for the roll-out. Nothing more should be changed, the network is in an optimal state. The series setup is just around the corner.
More Articles From This Series:
More Stories Like This:
The Right Decision: How Do You Know It’s Time to Switch to IP Communication in Public Transport?
Replacing analog technology in buses and trains with IP networks? This is a question that is currently occupying the minds of many public transport operators. We explain when is the best time to make the switch and what requirements must be met on...
Two Ways to Refit Vehicles in Public Transport
With increasing data volume and requirements for real-time data in public transport vehicles, IP-based communication has become a basic requirement for modern IT system architecture in vehicles. We use two examples to show how transport operators...
Practical Tips for Secure Networks on Buses and Trains
...Concepts and Levels of Security IT security in public transport must be understood as a holistic and overarching task. For example, the industry standard IEC 62443 describes the consideration of cyber security concepts from different points of...